Question (23002-18385)
If a renovator uses the required practices to remove containment and clean a work area, then performs successful cleaning verification, can the balance of the project then be done using uncertified workers and without reference to the work practices required by the RRP Rule?
Answer
Yes, as long as the balance of the project can be completed without disturbing a painted surface.